Construction
of Lake Levees and Roads for Management |
 |
|
 |
 |
 |
 |
 |
 |
 |
 |
Levees
were constructed in low land districts around the lake
to prevent flooding of Lake Biwa. |
|
Top£ |
‘ Cross
section
Levees were constructed to freeboard 1.2 meters over the design high
water level of +1.4 meters.
Furthermore, creating a large foreshore limited wave height on shore,
effectively lowering the height of the levees.
 |
B.S.L.= Biwako Basic Surface
Water Level |
|
|
|
 |
 |
Internal
Drainage
Facility Construction |
 |
|
 |
 |
River
Engineering |
 |
|
 |
 |
Dredging
of
the Seta River |
 |
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
Fourteen internal drainage
facilities (drainage pumps and sluice gates) were constructed
in six areas particularly vulnerable to flood damage in order
to drain water from rice paddies and the like that have been
inundated in a flood. |
To prevent flooding on bending
rivers, high-bedded rivers and the like, engi-neering projects
were undertaken to, among other things, raise embankments,
dredge and dig riverbeds and widen rivers. |
The Seta River was dredged
to increase its discharge capacity to facilitate water flow. |
Top£ |